How do you check the concrete mixing plant?
When you are in charge of a technician or a mixing plant, how do you determine whether the concrete mixing plant is qualified? Here, haomei has compiled a few validation criteria for you:
1. The mixing drum mixer if since the fall of concrete mixing plant type, it's discharging coil radial runout of not more than 1% of the inlet diameter, also check mixer on the quality of the steel sieve sieve and screen the reasonable size of the mesh and screen mesh and check the installation accuracy;
2. The transmission system of concrete mixing plan tshould be flexible and without abnormal sound;
3. The belt conveyor, bucket elevator and cantilever shovel in the concrete mixing station equipment should be smooth, flexible in operation, high in braking, no abnormal noise, no card chain;
4. It is also important to check the measurement system, to check the sensitivity and accuracy of the measurement system;
5. The inlet and outlet of the measuring hopper should be smooth, without the appearance of product and overflow;
6. There is no leakage phenomenon in the relief valve of concrete mixing station; The quality of cement tank is qualified; The matching line installation should be reasonable, the equipment installation should be correct.
1. The mixing drum mixer if since the fall of concrete mixing plant type, it's discharging coil radial runout of not more than 1% of the inlet diameter, also check mixer on the quality of the steel sieve sieve and screen the reasonable size of the mesh and screen mesh and check the installation accuracy;
2. The transmission system of concrete mixing plan tshould be flexible and without abnormal sound;
3. The belt conveyor, bucket elevator and cantilever shovel in the concrete mixing station equipment should be smooth, flexible in operation, high in braking, no abnormal noise, no card chain;
4. It is also important to check the measurement system, to check the sensitivity and accuracy of the measurement system;
5. The inlet and outlet of the measuring hopper should be smooth, without the appearance of product and overflow;
6. There is no leakage phenomenon in the relief valve of concrete mixing station; The quality of cement tank is qualified; The matching line installation should be reasonable, the equipment installation should be correct.