Do you know how to turn on and off concrete batching plant correctly?Reasonable safety switch is each part of the concrete batching plant switch breaks the accident and ensure the necessary premise that concrete plant equipment service life.
The boot order of concrete batching plant:
Check before starting the concrete plant;Open the water valve switch;Water pump and water storage bin door open – open air compressor discharge belt – open mixing console – open feeding belt ingredients (including aggregate, cement) – open water supply switch;
The shut down order of concrete batching plant:
Ingredients (including aggregate, cement) shut – water feeding off (belt material) – mixing main organs (concrete mixer tank material) – discharging belt off (belt material) – storage bunker doors – air compressor authority – cleaning agitation tank – shut off the water valve switch – turn off the total power.
HaoMei HZS series Skip Type Concrete batching Plant includes HZS50 (50m3/h) concrete batching plant, HZS75 (75m3/h) concrete batch plant etc.
Want to know more, welcome to call the hotline 86-0371-65621391