When the concrete batching plant is installed, the commissioning is an indispensable step.How to debug the concrete batching plant production correctly?
When commissioning the control system, first reset the emergency button, close the power switch in the electrical cabinet, switch on the circuit breaker, turn on the power switch of the control circuit, switch on the control room, turn on the power switch of the control circuit, check whether there is any abnormal phenomenon in the electrical system, Check immediately
Open the button of each motor, test run the motor steering is correct, if not correct should be adjusted immediately;
Start the concrete batching plant production pump, air pressure to meet the requirements after the button marked according to start each gas control door, check the action is flexible;
Zero the computer and adjust sensitivity;
Check the air compressor switch is normal, the barometer shows that the correct pressure relief valve will be adjusted to the standard range of the concrete mixer machine for commissioning to see if there is abnormal sound, whether the normal work of the various components;
In the process of commissioning the belt conveyor need to run in the process of checking the operation of each roller is flexible, to carefully observe the belt, can not swing, deviation, edging, skidding, deformation and so on;
When debugging the concrete batching plant must click the ingredients button to see if it is flexible and can be configured accuracy, and then adjust the ingredients reference.